With a start date of March 6, 2020, ReThink9 is currently ahead of its original May, 2021 schedule, with completion now expected in April, 2021.

Work completed or near completion includes retaining walls and masonry, curbs and gutters, and the installation of all underground utilities including power and communications conduit, street lighting conduit, storm sewers, drinking water main, sanitary sewer main and laterals.

Now underway is utility cable installation, roundabout construction, sidewalk and parking bay construction, base asphalt paving and fall landscaping.

Slated for early spring is raised crosswalk construction, streetlight installation, utility pole removal, final paving and landscaping.